Residences at Foundry Takes Shape: Windows, Roof, and More Completed in Portsmouth, NH

Recent milestones include:
🔸Installation of windows, doors, and sliders
🔸Completion of the roof, making the building watertight
🔸Excavated, placed, & backfilled the stormwater detention system

Inside the building, fire protection and HVAC rough-ins have reached the second floor, and work has started in the garage. KONE is advancing the elevator, and Metro Walls is framing common areas and sheathing tenant space exterior walls. Wall tops and fire taping on the upper floors are nearly done. We’re making great strides and can’t wait to share more updates soon!