Construction Progress at the New Hampshire Veterans Home Addition in Tilton

Construction continues to advance at the New Hampshire Veterans Home Addition in Tilton, NH, with exterior wall framing now taking shape.

Cold-formed metal framing is underway, outlining the 21 new single-occupancy rooms that will provide additional space for residents. As the building enclosure progresses, the next major step will be the installation of roof trusses.

The project team continues working toward getting the addition weather-tight ahead of the colder months. Great progress by everyone involved as this important addition continues to take shape.